Questions About the CPV Valley Energy Center? Please call: (877) 355-7010
"Efficiency is ever-increasing through technological advances, however our usage of available energy continues to increase and we must be willing to upgrade our energy infrastructure to meet future demand. CPV's project is very timely as Indian Point's current license to operate is being considered for renewal. If not renewed New York could experience a major energy shortage and this project can help mitigate that."
"Over the past five years CPV Valley Energy has, through a concerted effort to keep the public informed with open meetings, newsletters and an informational website, developed an unprecedented level of public support for its clean, natural gas powered electric generating facility. Undoubtedly, this project will foster an economic impact that will resonate well beyond Orange County and the lower Hudson Valley. Its location, which backs up against a major interstate highway and fronts on a highly traveled state road, is within the Priority Growth Corridor."
"According to both the Orange County Comprehensive Plan and the Town of Wawayanda's own planning policy, the area selected for the project is designated for commercial development. The project is a good use of the land."
"Hudson Valley Pattern for Progress is a regional planning and policy organization dedicated to enhancing quality of life by promoting a balance between economic development and environmental protection. To that point, we find the integration of a gas-fired facility to be a strong compromise in addressing and preserving those two goals. The people of this region, as always, require that their energy needs be met through thoughtful, environmentally conscious and economically prudent means and the CPV project meets those objectives."
As part of our continuing efforts to keep the community informed of the progress at the CPV Energy Valley Center in Wawayanda, we wanted to provide an important update.
Since completing commissioning of the CPV Valley Energy Center on our back up fuel in early May, the facility has been operational and providing reliability benefits to the electric grid by being available to operate in times of system stress. During the last heat wave, the facility was put on standby by New York’s grid operator to meet the soaring demand.
Millennium Pipeline Company completed construction and testing of the gas lateral on July 8th and received the final certificate to operate on July 9th. Federal and State regulators conducted numerous inspections throughout the pipeline construction and found no violations or infractions.
Now that gas is available, the final testing and commissioning phase is underway. The primary goal of this final phase is to operate the equipment on natural gas and enable the operation of both gas turbines and steam turbine together, which maximizes the efficiency of the facility. Once complete, the CPV Valley Energy Center will be one of the most efficient power plants in the United States. Although it is impossible to predict an exact date of completion, we are planning to complete all testing by mid-August. These testing and commissioning activities are a necessary step and are conducted in accordance with Federal and State air emission standards.
Once operating on natural gas, the CPV Valley Energy Center will displace older, less efficient fossil fuel generation operating today. By replacing that older generation, New York’s carbon emissions are estimated to be reduced by 1/2 a million tons per year. The CPV Valley Energy Center will also use less natural gas to create the same amount of electricity it displaces, which means less fuel will be extracted and imported into the state. As New York strives to achieve its goal of 50% renewables electric generation by 2030, the operational flexibility of the CPV Energy Center will greatly enhance the ability to balance renewables and help New York to meet its renewable goals.